In 2025, Chile, Argentina, and Peru present compelling mining investment opportunities, with project portfolios of $83.18B (Chile), $17.9B (Argentina, potential 2026-2028), and $53.7B (Peru). These investments are primarily driven by copper, lithium, gold, and iron, yet each country faces unique challenges (CochilcoChile Cochilco , Argentina.gob.ar, Ministerio de Energía y Minas, 2025).
- Chile leads with political stability and competitive costs ($1.90/lb copper) but has long permit times (7-11 years).
- Argentina attracts investors with RIGI (30-year fiscal stability, 25% corporate tax) but struggles with foreign exchange controls and permitting delays (5-10 years).
- Peru offers low production costs ($1.50-$1.70/lb copper) but is hindered by social conflicts and lengthy permitting (5-12 years).
Tax Incentives & Fiscal Stability
Chile (2025): Progressive mining royalty (0.5%-14%), R&D credits (35%-65%), and 10-15 years of fiscal stability. Investment focus: $15B in copper and $10B in lithium(Cochilco, InvestChile, 2025).
✅ Strengths: Political stability since 2003, attractive for ESG-focused investors.
❌ Weaknesses: Higher royalties increase costs; permitting takes 7-11 years.
Argentina (2025): RIGI (2024) offers 30-year fiscal stability, 25% corporate tax, VAT/export exemptions after 2-3 years, and foreign exchange flexibility after 4 years. Expected $15B in copper/lithium, but currency controls are a concern (Argentina.gob.ar, Bloomberg News, 2025).
✅ Strengths: Attractive incentives, strategic copper/lithium potential.
❌ Weaknesses: Political instability (Milei, 2027 elections), foreign exchange controls, permitting 5-10 years.
Peru (2025): Tax stability (20-30%), VAT exemptions, and R&D credits (up to 65%). Expected $6B-$8B in copper, gold, and lithium, but social conflicts slow progress (InvestPerú, Minem, 2025).
✅ Strengths: Lowest copper costs ($1.50-$1.70/lb), rich reserves.
❌ Weaknesses: Political volatility (2026 elections), social conflicts, permitting 5-12 years.
Operational Costs & Competitiveness
Chile: $1.90/lb copper (second quartile globally), high permitting times (7-11 years) increase CAPEX (S&P Global, 2025).
- Key projects: Escondida ($7B), Nueva Centinela ($4.4B), Codelco ($8.5B).
Argentina: $2.10/lb copper, high costs due to currency controls and permitting delays (5-10 years)(S&P Global, 2025).
- Key projects: Los Azules (McEwen, $2.7B), Mariana (Ganfeng, $980M).
Peru: $1.50-$1.70/lb copper, lowest in South America, but social conflicts and permitting delays (5-12 years) raise CAPEX(S&P Global, 2025).
- Key projects: Quellaveco ($5.3B), Toromocho ($1.3B), San Gabriel ($1.2B).
Permitting & Regulatory Delays
Chile: 7-year average, up to 11 years for complex projects (copper/lithium). Environmental regulations (DS 40, SEIA) and community consultationsslow progress (Cochilco, 2025).
- Projects like Los Bronces and El Morro face environmental opposition, delaying $15B in investments (Cochilco, 2025).
Argentina: 5-10 years due to provincial regulations, environmental approvals, and foreign exchange controls (Argentina.gob.ar, 2025).
- Projects like Los Azules and Mariana might face delays, impacting $17.9B in potential investments (Bloomberg, 2025).
Peru: 5-8 years on average, up to 12 years for complex copper/gold projects, due to environmental laws (DS 017-2020) and community resistance(Minem, 2025).
- Projects like Conga and Tía María face social conflicts, delaying $20B (Minem, 2025).
Political Stability & Social Risks
Chile: Stable since 2003, with municipal elections in 2025 and fiscal predictability, but ESG regulations add permitting challenges(El País Chile, 2025).
- Judicial cases impact major projects like Dominga (Cochilco, 2025).
Argentina: Unstable under Milei (2023-2025), 2027 elections could impact RIGI, and foreign exchange controls since 2011 create uncertainty (Argentina.gob.ar, 2025).
- High risks due to regulatory uncertainty, affecting projects like Los Azules (Bloomberg, 2025).
Peru: Volatile since 2021, frequent leadership changes, 2026 elections bring uncertainty (BCRP, 2025).
- Social conflicts in Cajamarca, Áncash, and Arequipa delay $20B in projects (Minem, 2025).
Strategic Investment Opportunities (2025-2030)
- Chile: $15B in copper (Escondida, Nueva Centinela) and $10B in lithium (Codelco-SQM, CEOL), if permitting accelerates and ESG rules remain stable (Cochilco, 2025).
- Argentina: $15B in copper/lithium (Los Azules, Mariana), if currency controls are eased and permitting improves (Argentina.gob.ar, 2025).
- Peru: $6B-$8B in copper/gold/lithium (Quellaveco, Toromocho), if social conflicts and permitting hurdles are resolved (Minem, 2025).
Investor Recommendations
✅ Chile: Prioritize stability and ESG appeal, but be prepared for long permitting (7-11 years).
✅ Argentina: Consider RIGI’s tax incentives and lithium/copper potential, but monitor currency controls and political shifts.
✅ Peru: Leverage low costs ($1.50-$1.70/lb copper), but manage social risks and permitting delays (5-12 years).
Diversification is key to mitigating regulatory, political, and social risks (S&P Global, 2025).
Where to Invest in 2025?
Chile, Argentina, and Peru each offer unique mining opportunities in 2025.
- Chile leads in stability 🏛️
- Peru wins on low production costs 📉
- Argentina shines with strong investment incentives 💰
But permitting delays (7-12 years), political shifts, and social conflicts will shape the fate of $46B-$48B in total investments from 2025-2030.